Key developments in the past 2 weeks:
- The closing date is set for July 27th (Yay!)
- The dry wall is finished
- The flooring has been installed in the bathrooms and utility room
- The base-board trim is almost completely installed
- The garage door is installed
- All of the interior doors have been installed
- The fire place mantle and marble exterior has been installed
By the end of next week, they should have the caulking done, started applying the first coat of paint, started or finished installing cabinets, started installing plumbing fixtures, and installed locks on the doors so the house can be locked. Below are some pictures of the recent progress.
The outside is pretty much done with the exception of the porch columns!
This is all very exciting stuff! Thanks for the photos and updates!
ReplyDeleteIt's so great to see your house coming into being! I love that you wrote bible verses in the foundation - what a wonderful way to bless your house. I look forward to more updates - best to you both as you anticipate your new home!